On the nose November 2018 Stages of work on the construction of the foundation and the base completed. Before the frost like anything else in time, namely to perform backfill the basement of the purchase and the building material for the construction of the house.

The first thing I took fertile soil inside the structure and evenly scattered over the area of ​​its total area, thereby raising the level of humus 10 centimeters.

Brought 15 tons. Coarse sand.

After making of check Wheelbarrow disassembled pallet has started filling a base.

After 30 brought wheelbarrows sand layer is leveled and paced electrical compactors again.

Based on my experience I would say honestly that such compaction is not effective, because after all these definitively manipulation, standing for all winter under the constant onslaught of snow and rain - more compacted sand and sat centimeters 5.

The height of the basement of my house was 55 cm. When compacting the sand layer 3 turned by 15-20 cm. each.

Two days and 70 sq.m. grounds for Ground floors are ready.

instagram viewer

Now, with peace of mind, you can wait for the next construction season!