This is exactly what the title of the question from the reader Andrey sounded like.
I continue to publish the questions that readers asked me. For new dear readers who came to my channel for the first time, I inform you that this is already 29 such publication. You can familiarize yourself with some other questions and answers to them by clicking on the links at the bottom of this article.
The text of the question itself was as follows:
Installed a new 3-phase energy meter CE307 R33.043. There are no readings on the scoreboard, there is light in the house. The networkers connected the cable to the support and said that something was assembled incorrectly, but did not explain what. Discard the wiring diagram.
I gave the following answer to this question:
Here is the wiring diagram for the electricity meter you have installed:
Please note, be sure to check all connection diagrams with the passport of the electricity meter installed in you. The thing is that these are materials from the official manufacturer of Energomer. If you have installed, nevertheless, the equipment of another company, there may be some differences, so it is better to double-check.
Also note that the electricity metering unit is on the balance sheet of the managing company, so you yourself do not have the right to change the connection method or make any adjustments.
It is better to contact the power supply organization with a corresponding statement about the problems found in the operation of the electricity metering unit and a request to take appropriate measures. This is their job and they are responsible for it, so you better not risk getting yourself penalized.