3 method a small saving on the foundation tape without loss of quality.

  • Dec 24, 2019

Good day, dear guests and subscribers!

Since I am often confronted with different people close to the low-rise construction, as building teams, and with the owners built houses, which have a different social status, but who decided to build, in this material are ways to reduce the cost of ribbon foundation.

In addition, there are engineers and designers more "old school", which can confirm that such practices are taking place without any loss of quality !!!

Now you're ready!

The thickness of the foundation wall

It is believed that the foundation should be wider than, or at least the same as the wall of the house. This is not true, as the main element of the foundation is cast tape at its base, and wherein the width to be calculated to a fully transfer the load from the house to the ground without subsidence and foundation wall - a structure in which, and will be the future walls.

In all three versions the figure - the foundation of the same quality! In the first case - the concrete is poured into the excavated trench (preformed) - savings are achieved through the method formless, but uses more concrete due to wall thickness!

instagram viewer

Variant №2 - the most common of the represented. Poured in two stages: first the basic cast tape, then the foundation wall - as a basis for the construction of walls.

Option №3 - rarely used, but few had seen with their own eyes. In small houses savings of about 4-5 cubic meters. meters of concrete, and it is about 17 -.. 25 thousand rubles, and also there is a place for warming without a strong projection of the plinth. The protruding member (flange) of a height of about 7-10 cm. and can be executed in two variations. In this case, calculation is needed working reinforcement at the top (highlighted in red) to avoid wall foundation element cleavage "shelves".

rubble concrete foundation

Crushed stone as compared to ready-mixed concrete - cheaper by 2-3 times (depending on the price of the supplier and the distance from the place of construction to the quarry for stone extraction).

Organization of work being done in the following way: Before pouring the concrete into the formwork or trench is expanded along the perimeter of the future house a stone of different fractions (from 50 mm. to 300 mm.). Further, in the process of pouring the concrete mix into the trench, it vkidyvaetsya. Of course, pre-calculated amount of stone and is 1 part 4-5 concrete parts. Thus, instead of concrete cubes 50 get 40 cubes and cubes 10 rubble. The gain in price by 10 cubes of concrete savings of about 10 000 rubles.

Rubble concrete foundation (Photo from Internet)
Rubble concrete foundation (Photo from Internet)
There is a forgotten option laying of the foundation stone "of our ancestors" (see. pictured above), when production work is carried out in layers, alternating with masonry stone laying solution. Here stone laying takes the lion's share of the time, but saving money on the grout cover these costs!

Savings on the formwork

One way to save on production work, and at the same time comply with the design data of the required bearing area on the ground - to organize the casting of the foundation in a single step.

Option a) - it is widely used in private construction. The organization works in two stages: first of all filled with a monolithic tape, the second action is set formwork and poured the foundation wall, etc. - dismantling of formwork and backfilling.

Option b) - Excavation made with the broadening of the base of the foundation, usually trimmed with a bayonet spade, after the organization of the main trench. It applies only in the case if the ground allows you to work without showering, to comply with the necessary foundation bearing area on the ground.

This variant b) times cheaper work than a), but slightly increased flow rate of concrete mix (about 2-3 cubic meters) due to the chamfered corners. Filling is done directly in the ground.

results

In fact - everyone's business, choose a foundation and how to produce works on the foundation, listen to the designers, or rely on their own.

One should understand that to save a substantial amount on a quality foundation still does not work, otherwise it will result the detriment of quality, but the fines may be provided, for example by wrapping shuttering boards in the film for further use))).

But I would not recommend to save on the fixture!

In my case, I first saw the foundation itself, then in order to cross-check himself hired the designer for this calculation, and it cost me only 2,500 rubles. Our calculations have converged, and I am satisfied!
When I Works made a trench for option b), as the ground allowed me enough to step aside and crop wall.

You can see on my channel to this publication the following link:

"The trench for continuous footing"

Thank you for your attention!

"How to settle the foundation?"

"Base of rubble stone and concrete"

______________________

If you liked this article, place and Likesubscribe to my channel!